R B Plant has recently completed a major storm water project for Syngenta.
This environmental project comprised improved containment, including the
creation of watertight lagoons, a new site transfer system and treatment
plant modifications.
The main project followed a series of design studies providing the
details required for board level decisions and approval.
"R B Plant’s design and construction work to achieve this large and
difficult project within budget and programme is a credit to their team and
that of Syngenta. Working with our engineers and site personnel, the work
was achieved with minimal site disruption.
We at Syngenta were delighted to present R B Plant with a Contractors
Safety Award at a ceremony last year. The new storm water facility has been
tested fully a number of times since it was commissioned each time with
absolute success.
Through innovation and fully understanding our business needs, R B Plant
made us considerable cost savings by clever use of existing facilities,
equipment and features".
Senior Project Engineer, Syngenta
|